Location: Shaoyang, Hunan;
The Huangdailing wind power project is located in Jianjialong Town and Shuangfeng Township in Shaodong City, Hunan Province. It achieved full capacity grid connection in October 2024. The project installed a total of 19 wind turbine units, all utilizing 690V water-cooled dual-feed wind power converters supplied by Hopewind, covering multiple converter models including 5.0MW, 5.6MW, and 6.25MW. After completion, the project's annual power generation reaches 236 million kilowatt-hours. Furthermore, adhering to eco-friendly principles, the wind farm implemented vegetation restoration using a combination of hydroseeding with grass seeds, trees, and shrubs, cumulatively restoring vegetation over 39.32 hectares of land.