Location: Heilongjiang;
This project has a total installed capacity of 200 megawatts. As China's first onshore wind power project to batch-use 10MW units, it set a new record for the largest capacity commercial wind turbine deployed onshore in China. This significantly reduces per-watt cost and improves land use efficiency for the wind farm. In this project, Hopewind supplied all 20 units of 10MW three-level air-cooled dual-feed converters. After commissioning, the project is expected to utilize wind energy resources for 3,288 hours annually, with estimated annual power generation reaching 530 million kilowatt-hours.