Time: 2023
Location: Wuzhong, Ningxia
Scenario: Energy storage station in a low-temperature environment
The grid simulator leased by Hopewind is utilized for the grid connection performance test at an energy storage station in Wuzhong, Ningxia. The test of the on-site energy storage units covering all working conditions is completed in just 3 days, effectively assisting the new energy station in obtaining the grid connection permit and achieving smooth grid connection and power generation.