Location: Yongde County, Yunnan
This project marks the first photovoltaic investment by POWERCHINA New Energy Group in Yongde County. With an AC-side installed capacity of 70MW, it utilizes 313 Hopewind 225kW inverters. Upon completion, the Xiaomengtong Town 70MW project is expected to generate approximately 111.04 million kWh of electricity annually, saving about 33,500 tons of standard coal and reducing CO₂ emissions by roughly 87,700 tons each year.